The area of the project is 10,890 m2 located in Aydın Province, Kuyucak District, Çobanisa District, Tekzeytin Mevkii.
The land related to the activity phase of the project was purchased, the applications of official institutions were completed and the EIA Positive Certificate and Associate Degree Certificate were obtained.
Electrical Power Generation
Fertilizer Production
Equivalent to Electricity Consumption
Aydin Kuyucak Biogas Power Plant which will start production in 2021 within the scope of YEKDEM will have installed capacity of 2,190 MWm / 2,134 MWe. 131.400 tons of cattle and hen fertilizer is fermented in our power generation plant in a year and electricity of 14.938,00 MWe/year will be produced. The annual organic solid fertilizer production capacity of the facility is approximately 12.450 tons/year
Our biogas facility investment is in the phase of EMRA Production License and public works permit.